Skip to main content
  Press Releases
  E-Notifications
  Staff Directory


 
Printer Friendly Version 
Roadwork Projects in Cheltenham Township (2nd UPDATE for 6/19)
Posted Date:
6/19/2018
Harrison Ave. at Gimble Field will be closed this afternoon (June 19) and tomorrow (June 20). Please read on for a second roadwork update for June 19.

Kehoe Construction will be milling/paving Ryers Ave. between Jefferson Ave. and Beecher Ave. starting tomorrow, Wednesday, June 20. The work should be completed by the end of the week.

______________________________________________________________________

RIII Construction will be closing down Harrison Ave. at Gimble Field this afternoon, Tuesday, June 19, and all day Wednesday, June 20, for installation of the sanitary sewer.


______________________________________________________________________

WEEK OF JUNE 18 UPDATE: The document above -- Week of June 18 Update -- details road work to be done in the Township next week. Work on Church Rd. will be completed next week and work on New Second Street will take place over the next two weeks.

___________________________________________________________________

As part of the Township's Infrastructure Improvement Program, Aqua PA has begun work to replace existing water mains on a number of streets. Please see the letter that came out in May above (May 14 Letter) detailing the locations and timing, as well as other information.


__________________________________________________________________


Crews will only be working services on Church Road and New Second Street this week. Please see the attached document, "Week of June 4 Update" for details.

____________________________________________________________________

Dear PECO Customer:

This coming Thursday night, May 24th, we will be working through the night in order to complete the gas up of the new main in your neighborhood.

·        Work is expected to begin May 24th, 2018 in the area of Church Road from Hammond to New Second Street and New Second Street from Church Road to Tookany Creek Pkway from 9 a.m. – 3 p.m.

·       Work will then resume from 7 p.m. through approximately 5 a.m. with PECO crews to finish the energizing of the new gas main.

·       During this time you may see and hear our crews and equipment. We apologize for any inconvenience and will minimize our disturbance as much as possible.

·       Church Road from Hammond to Kingston will be shut off and detoured during these hours.

·       Local traffic will be able to access and utilize Hammond Rd and Kingston Road and we will facilitate traffic for those who live on Church Road.

·       Residents affected by this project will have a hard copy of this letter hand-delivered to their residence (to their front door). 

This work will be performed by Henkels & McCoy, a qualified PECO contractor. If you have any questions regarding this project, please contact Anthony Tornetta of Henkels & McCoy at (267) 398- 8707 or Keith Harper at (267) 246-6696.

Thank you,

Henkels & McCoy

_____________________________________________________________
For updates on the PECO Gas Capital Replacement locations in the Township for the week of 5/21/18, see the attached PDF file above titled "PECO Bi-Weekly Update 5/21/18."
______________________________________________________________
As indicated yesterday, weather permitting, the Tookany Parkway will be closed on May 23 for paving from 7 am to 7 pm. Specifically, the work will take place between Central Ave. and Jenkintown Rd.
______________________________________________________________
Depending on the weather, Tookany Parkway will be closed for paving on Wednesday, May 23 from 7:00 am to 7:00 pm.
______________________________________________________________

For updates on the PECO Gas Capital Replacement locations in the Township for the week of 5/7/18, see the attached PDF file above titled "PECO Bi-Weekly Update 5/7/18."


The main work on the current job (Church and New Second Street) was slowed down by some rock, but will be complete with the main installation on Monday. Following that, there will be prep work to get ready to gas up the new main. We hope to pull in the end date by accelerating the service work.

________________________________________________________________

Route 73, Church Rd.
  • Ashbourne Rd.
  • Washington Lane
  • Willow Grove Ave.
Crews will restrict travel lanes on these state highways to patch areas of deteriorating pavement. Motorists are advised to be alert of this moving operation and to expect intermittent lane closures and possible slowdowns when driving near work crews. All activities are weather dependent.

PennDOT would also like to remind motorists that potholes and other roadway concerns on state roads can be reported by calling 1-800-FIX-ROAD or visiting www.penndot.gov and clicking on “Submit Roadway Feedback.”

______________________________________________________________

Aqua will replace the existing water main on New Street between Glenside Avenue and a point 300 feet s/o Glenside Avenue.

The project is scheduled to begin the week of March 5, 2018 with completion expected in May. Construction will typically take place week days between 7AM and 3PM.

Following the installation of the new water main, there will be a period of time during which the main will be chlorinated and tested before being put into service. During this phase, activity on the job site will be limited. Once testing has been completed, Aqua will transfer each water service and any fire hydrants onto the new main. It is important to note that the trench will be covered with temporary black top at the end of each work day. Once all of the activity described has been completed, permanent restoration will follow in about 30 to 60 days.

Access will be provided for emergency, mail, school buses and trash services. Residents will have access to their properties but at times will need to enter from a different direction due to changing work zones.

INFO: Mike Staerk, Superintendent of Construction
215.659.2505 ext. 56005.
_______________________________________________________________

Church Road will be closed between New Second St & Hammond Rd on weekdays between 9AM & 3PM beginning Feb 21, 2018 for a PECO project. The detour (see attached file at top titled "Church Road Detour") will be in place until the expected project completion at end of April.

INFO: Keith Harper of Henkels & McCoy at 267-246-6696.
_____________________________

PECO will be installing new gas mains in several areas. Work is expected to begin Oct 23, 2017 and be completed in 22 weeks. Work hours are 7:30AM – 3PM (9AM – 3PM on State Roads).
Work locations are:
New Second Street from Tookany Creek Parkway to Church Road
Church Road from New Second Street to Hammond Road
Hammond Road from Kingston Road to cul-de-sac
Kingston Road from New Second Street to Hammond Road
INFO: Contact Brian Hettrick of Henkels & McCoy at 215-852-8402.

_______________________________________________________________

The Township's 12-month project to replace nearly 4 miles of its public sanitary sewer system, called Interceptor A, between Old York Road and Central Avenue, will require temporary road and park closures in the active work zones.

Tookany Creek Parkway is closed between Beryl Road and Central Avenue until approximately Memorial Day 2018.

Updates & More Info:
Department & Services » Sanitary Sewer System » Replacement of Interceptor

______________________________________
Greenwood Avenue & Church Road Left-Turn Arrow

The Township installed a left-turn arrow for westbound Church Road drivers turning towards Route 309 on September 28, 2016. Although unlikely to completely eliminate traffic backups in the area, the left-turn arrow should provide some relief to traffic flow until PennDOT completes a more extensive signal and intersection upgrade that includes creating a dedicated left-turn lane. PennDOT’s project is scheduled to go out for bid in 2018.


_____________________________________________

EASTON ROAD AND ASHMEADE ROAD BRIDGE CHANGES
Jan 14, 2016

As a result of PennDOT inspections, Cheltenham Township officials announce changes that will impact traffic on two local bridges, one on Easton Road and the other on Ashmeade Road.

First, the weight limit of the Montgomery County-owned Easton Road bridge located near the Toxany Avenue intersection has been lowered to 13 tons because the bridge is considered “structurally deficient and functionally obsolete.” Trucks over 13 tons should follow posted detours using West Glenside Avenue and Limekiln Pike. Later this month the Montgomery County Commissioners are expected to authorize the first steps in the bridge rehabilitation process, which could take approximately three years to complete.

Ashmeade Bridge Second, Cheltenham Township has eliminated one of two west-bound lanes on Ashmeade Road between the Philadelphia border and Tookany Creek Parkway. To help compensate for the lane loss, the left-turn arrow at the parkway intersection has been extended. In addition, the double yellow line has been shifted to the center of Ashmeade Road, and reflective delineator posts have been installed along the shoulders of the bridge.  The bridge weight limit of 5 tons has not changed. The new traffic pattern will remain in effect until the township replaces the bridge, expected to begin later this year.




 

 
 
 
Cheltenham Township   ~   8230 Old York Road   ~   Elkins Park, PA 19027   ~   Hours: M-F, 8AM-4:30PM
Phone: 215-887-1000   ~   Fax: 215-887-1561
Home   |  About Us   |  Government   |  Departments & Services   |  Residents   |  Business   |  I Want To
Site Map   |   Contact Us   |   Disclaimer   |   Powered by MunicipalCMS
Sign up for enews Facebook Get our RSS feeds